Site Photo July 30,2013

Site Photo July 30,2013

7-30-13

Installed to date:

415 (70%) Heater Wells (HO)

403 (73%) Vapor Extraction Wells (VEW)

54 (56%)  Temperature Monitoring Points (TMP)

38 (59%) Pressure Monitoring Points (PMP)

2 (29%) In-situ Thermal Remediation (ISTR)