Drilling Continues

Posted on: May 13th, 2013 by Jon Turner No Comments

5-13-13-1

 

View from southwest looking to the northeast.

Drilling continues. The vapor extraction wells are located approximately 3 feet from the electrically powered heater wells. In addition the team is installing Temperature Monitoring Points and Pressure Monitoring Points. To date we’ve installed: 109 Heater Wells (HO), 105 Vapor Extraction Wells (VEW), 9 Temperature Monitoring Points (TMP), and 9 Pressure Monitoring Points (PMP). Also, note the air monitor in the foreground.